What does it do?

Material Requirements Planning (MRP) is a computerized system developed by Joseph Orlicky in the 1970s that calculates material requirements based on master production schedules and bill-of-materials data.

MRP determines what materials to buy, how much to order, and when to order them to meet production demand while minimizing inventory carrying costs. It became a foundational technology for manufacturing planning and later evolved into manufacturing resource planning (MRP II) and enterprise resource planning (ERP) systems.

The intuition behind the method

Imagine a furniture manufacturer receiving an order for 100 dining tables, each requiring 4 chairs, a tabletop, 4 legs, and 8 fasteners. Rather than manually calculating and ordering each component, MRP works backward from the end-product demand. It explodes the bill-of-materials, accounts for current inventory levels and lead times, and generates purchase orders and work orders timed to ensure components arrive exactly when needed for assembly. For example, if table assembly takes 1 week and leg production takes 2 weeks, MRP schedules leg production to start 2 weeks before assembly. The system handles hundreds of products and thousands of components, making it far superior to manual planning in complex manufacturing environments.

History

Joseph Orlicky pioneered MRP in the 1960s–1970s at Westinghouse, developing the first computerized logic for material planning. His work was formalized in the 1975 book 'Material Requirements Planning.' MRP gained widespread adoption in the 1980s and 1990s as computers became ubiquitous. The American Production and Inventory Control Society (APICS) standardized MRP terminology and best practices. MRP evolved into MRP II (Manufacturing Resource Planning) to include capacity planning and eventually into modern ERP systems (SAP, Oracle, NetSuite) that integrate MRP with accounting, finance, and supply chain management.

When to use it

MRP is essential for manufacturers producing multi-level products with complex bills-of-materials and multiple sourcing options. Apply MRP when lead times are significant (so advance planning matters), when inventory carrying costs are high, or when coordinating procurement with production is critical. MRP works best in make-to-stock and assemble-to-order environments with relatively stable, predictable demand. Less effective in high-mix, low-volume job shops or truly demand-driven environments (where kanban may be preferable).

Limitations and considerations

  • Assumes stable, predictable demand; performs poorly with highly seasonal, erratic, or customized demand
  • Requires accurate, current bill-of-materials and inventory data; system outputs are only as good as input data
  • Does not account for capacity constraints in detail; infinite capacity assumptions can lead to unrealistic schedules
  • Can generate nervous schedules (frequent changes to planned orders) if not tuned properly, creating supply chain instability

Source conditions do not replace independent scientific review or validation by an analysis engine.

Strengths

  • Automatically calculates material requirements for complex, multi-level products, reducing planning errors and manual effort
  • Schedules material purchases and production orders to arrive just-in-time, reducing inventory carrying costs
  • Provides visibility into capacity constraints and schedule conflicts, enabling better decision-making
  • Integrates demand (forecasts, customer orders) with supply planning, creating coordination across sales and operations
  • Foundation for advanced planning systems (APS) and enterprise resource planning (ERP) platforms

Applications

  • An automotive supplier uses MRP to plan procurement of hundreds of components for multiple vehicle programs, ensuring on-time delivery to OEM plants while maintaining inventory turns of 15+
  • An appliance manufacturer implements MRP to synchronize production schedules across multiple plants, reducing lead time from 6 weeks to 3 weeks for made-to-order refrigerators
  • A telecommunications equipment manufacturer uses MRP to manage dual sourcing of critical semiconductors, automatically switching suppliers based on availability and lead times
  • A heavy equipment builder applies MRP to manage complex assemblies with 50,000+ bill-of-materials levels, enabling accurate delivery commitments and reducing excess inventory by 20 percent

How it works

How it works

1

Gather master production schedule (MPS) data: planned orders and forecast for end products.

2

Retrieve bill-of-materials: the recipe showing every component (direct and indirect) required for each end product.

3

Perform material explosion: for each level of the product structure, calculate net material requirements (gross demand minus available inventory and scheduled receipts).

4

Offset quantities by lead times and generate planned orders for procurement and production at appropriate times.

5

Analyze planned orders, identify conflicts (demand exceeds capacity), and adjust schedules or inventory plans accordingly.

Common pitfalls

  • Relying on MRP outputs without safety stock or buffer analysis; lead-time variability and demand uncertainty are not fully captured
  • Using outdated or incorrect bill-of-materials data, causing MRP to generate material requirements for non-existent or obsolete components
  • Failing to incorporate capacity constraints and supplier constraints into MRP planning, resulting in unrealistic schedules that cannot be executed

Frequently asked questions

How is MRP different from ERP?

MRP is a planning algorithm focused on material requirements and scheduling. ERP is a broader enterprise software system that includes MRP as one module, plus accounting, finance, HR, and CRM functions. Modern ERPs use MRP logic but integrate it with real-time data and other business processes.

Can we use MRP in a make-to-order environment?

Yes, MRP adapts to make-to-order: the master production schedule is driven by customer orders instead of forecasts. The advantage is precision—you calculate exact material needs for exact customer specifications. The challenge is shorter planning horizons and less time to aggregate demand across orders.

What is MRP nervousness, and how do we prevent it?

MRP nervousness occurs when small changes to the master schedule trigger large changes to planned orders throughout the supply chain, destabilizing suppliers and inventory. Prevent it with time fences (planning horizon divisions), frozen schedules for near-term periods, and safety stock policies that absorb minor demand variations.

Do we still need MRP in a lean manufacturing environment?

MRP and lean are complementary. Lean reduces variability and simplifies scheduling (e.g., through kanban), which can make MRP unnecessary for some materials. For long-lead-time or complex materials, MRP remains valuable. Many organizations use a hybrid: kanban for high-volume items, MRP for long-lead or low-frequency components.

Related methods

Sources

  1. Orlicky, J. (1975). Material requirements planning: The new way of life in production and inventory management. New York: McGraw-Hill.

    Open publication reference
    Copied.
  2. APICS (2020). APICS Dictionary (16th ed.). Chicago: APICS.

    Open publication reference
    Copied.